| |
|
Inserting
live cutting pocket
|
Placing
next lift of riprap

|
Inserting
live cutting pockets
|
Checking
elevation of riprap

|
| |
|
Excavated
trench for vegetated riprap
|
Live
cuttings placed in trench, trench being backfilled
with topsoil and native soil material
|
| |
Protective
wooden sheets placed
|
Placing
riprap to final road sub-grade

|
| |
| Riverbank
Sections 2 and 1A:
Vegetated
riprap in Sections 2, constructed in 2006, and
1A, constructed in 2008, consisted of only one
row of the brush layers. The procedure was similar
to that outlined above for the vegetated riprap
brush layer in section 1.
A
trench was first excavated in the road sub-grade
behind the placed riprap, followed by:
1)
Placement of live cuttings in the trench.
2)
Watering and addition of soil amendments.
3)
Backfilling of the trench using topsoil and
native soil material.
4)
Placement of protective wooden sheets.
5)
Placement of riprap to complete the road sub-grade.
In
Section 2, a mechanically stabilized earth (MSE)
wall was constructed above the vegetated riprap
(see photos below).
In
Section 1A, a strip of burlap was placed over
the riprap prior to placement of the live cuttings
as added protection and to better hold the soil
before placement of the protective wooden sheets.
|
| |
Excavated
trench Section 2 vegetated riprap
fall
2006
|
Live
cuttings placed in trench
|
| |
Back-filling
trench

|
MSE
wall constructed above vegetated riprap, cobbles
were later placed over wooden sheets

|
| |
|
Excavated
trench for Section 1A and placement of cuttings,
spring 2008
|
Live
cuttings placed in trench with burlap
|
| |
Trench
back-filled and sand placed over live cutting
on riprap
|
Trench
back-filled to final sub-grade
|
| |
Completed
road
|
| |
| Survival
and Growth:
The
survival and growth of vegetated riprap brush
layers installed along the riverbank has been
excellent to date. The survival of the lowest
rows of live pockets installed in Section 1 has
been poor, due to a prolonged flooding period
in the spring of 2006 and 2007. Survival of the
upper rows has, however, been relatively good.
In areas where the cuttings remained above the
water during flooding, survival has been good.
Link
to: Main
Riverbank Restoration Project Page |
| |
Lower
pockets in Section 1 under water during flooding,
spring 2006
|
Section
1 summer, 2006
|
| |
Section
1, summer 2006
|
Section
1, summer 2008
|
| |
Section
1, summer 2008
|
| |
|
| |
Section 1 South, summer 2010

|
| |
Growth on live cutting planted in riprap, 2010
(note: original live cutting in red circle)

|
Salix lasiandra clump growth 2010

|
| |
Section 1 North, summer 2010 |
|
|
| |
Section
2 during flooding, spring 2007, note upper portion
of cuttings above water level
|
|
|
| |
Section
2, summer 2008
|
|
|
| |
Section
2, summer 2008
|
Section
1A, spring 2008
|
| |
Section
1A, summer 2008
|
| |
Section 1A South, summer 2010
|
|
|
| |
Section 1, summer 2010

|
| |
Section 1A, summer 2010

|
| |
Section 1, 1A and 2, summer 2010

|
| |

Copyright © 2010
Terra Erosion Control Ltd.
Vegetated Riprap |
|